Metro Heights

Location – Baltimore, MD
Year Completed – 2018
Owner – Enterprise Housing Corporation
General Contractor – Harkins Builders

Project Size – $1,400,000
Scope of Work:

Provided sitework package including site utilities (15” storm drains & {180f} water lines), and 140lf sewer sanitary PVC.

Calverton EMS

Location:
Baltimore, MD
Year Completed:
2021
Owner:
Maryland Stadium Authority
General Contractor:
Whiting-Turner

Project Size:
$6,100,000
Scope of Work:

Provided sitework package including site utilities (storm drain {4,520lf}, ductile water line {1,160lf} and SDR35 sanitary sewer lines {364lf}) and 46,200sf of 5” sidewalk concrete, 2,307sy of 5” asphalt and 1,997sy of 4.5” asphalt.