John Rurah Elementary/Middle School
Location – Baltimore, MD
Year Completed – 2020
Owner – Maryland Stadium Authority
General Contractor – MCN Build, LLC
Project Size – $3,000,000
Scope of Work:
Provided sitework package including site utilities ({2,460lf storm drains & {900lf} sanitary, {250f} of 8” ductile water lines), concrete for curbs and gutters (curb concrete {350lf}, {1,500sf} heavy-duty concrete pads).
UMMS Midtown Campus Outpatient Center
Baltimore, MD
Year Completed:
2021
Owner:
University of Maryland
General Contractor:
Clark Construction
Project Size:
$1,500,000
Scope of Work:
Provided sitework package including site utilities (ductile water {820lf} and {60lf} of 8” sanitary sewer lines).