Calverton EMS
Location – Baltimore, MD
Year Completed – 2021
Owner – Maryland Stadium Authority
General Contractor – Whiting-Turner
Project Size – $6,100,000
Scope of Work:
Provided sitework package including site utilities (storm drain {4,520lf}, ductile water line {1,160lf} and SDR35 sanitary sewer lines {364lf}) and 46,200sf of 5” sidewalk concrete, 2,307sy of 5” asphalt and 1,997sy of 4.5” asphalt.
North Avenue Gateway II
Baltimore, MD
Year Completed:
2018
Owner:
LIHTC Housing
General Contractor:
Harkins Builders
Project Size:
$1,500,000
Scope of Work:
Provided sitework package including site utilities ({100lf} of 6” waterline and {200lf} of 6” Sanitary lines), site concrete and asphalt paving ({650lf} concrete for curbs, {10,000sf} of asphalt paving).